Expected project duration - 1st Oct to 15th Nov
- [All] Design (4 days)
- [All] Initialize Project (2 days)
- [Server] User Account (3 days)
- [CA, Extension] User login and register (3 days)
- [Extension, Server] Highlighting (4 days)
- [CA] List Highlights of a user (4 days)
- [All] Testing (2 days)
- [All] Design (3 days)
- [Server, CA] Create note on demand (2 days)
- [Server, Extension] Adding tags and categories to highlights with search feature (5 days)
- [CA] Search feature (5 days)
- [All] Testing (2 days)
- [All] Design (2 days)
- [Extension] Rehighlight text in Browser (2 days)
- [Extension] Highlight in Google Search (2 days)
- [All] Commenting feature on a highlight with edit comment (4 days)
- [All] Testing (2 days)
- [All] Finalzing Documentation (4 days)
- [All] Deployment (2 days)